Project: Hollister Entrance Bridge, Expansion Joints
Owner Contract: Donald Bolton
Location: Libertyville, IL
Engineer Contact: Walker Restoration Engineers, Sanjay Pandya
Scope:
Remove and replace the bridge expansion joints
Concrete at the post-tensioned tendon anchors was removed and re-cast to accept new ADA
Seals were installed in two phases
Site Conditions:
The pedestrian bridge is at the entrance to the Corporate Headquarters
The entrance had to remain open to pedestrian
Compliant seals traffic throughout the project
|