Project: Alabama Department of Transportation IM-I059(306)
Location: Birmingham, Alabama
Engineer: Alabama Department of Transportation
Completed: July 2002
Scope:
1.30 mile long bridge, polymer concrete overlay, repair and re-striping of the bridge deck
427,000 S.F. shot blast cleaning
427,000 S.F. polymer concrete overlay over the south bound lanes
Installed over 4,000 L.F. expansion joints
Miscellaneous concrete repairs
Site Conditions:
All work performed at night between 8pm and 6am while maintaining traffic in open lanes
All lanes reopened to traffic each morning by 6am
Interstate bridge in downtown Birmingham
Project completed in 37 working days
|